THE MILSON

THE MILSON

PROJECT OVERVIEW

Description of work

Remedial waterproofing to SW corner of residential tower – fully occupied. Works involve balcony replacement, cavity flashing , glazing seals, storm moulds, facade paint cladding and glazing replacement.

Particular challenges and problems overcome

Awkward access, very high winds in location, fully occupied units

Value add to client

Long term experience and familiarity with the building – over 15 years able to assist and direct contractors as to best and practical issues for access and repair

Project Value: 550,000
Start Date: February 2023
Completion Date: October 2023