17 WYLDE STREET, POTTS POINT

17 WYLDE STREET, POTTS POINT

PROJECT OVERVIEW

Description of work

Completion of works to satisfy a fire order, including the installation of sprinklers , fire extinguishers and a pump room.

Particular challenges and problems overcome

Understanding scope of work and ensuring City of Sydney requirements were met

Value add to client

Navigating complexity of a previous contractor dispute and resolving outstanding issues

Client: 17 Wylde St Co-operative Limited
Project Value: 300,000
Start Date: June 2023
Completion Date: October 2023